WAUBONSEE COMMUNITY COLLEGE

Downtown Aurora Campus

Case Study

Partnering with Waubonsee Community College to make critical infrastructure upgrades to their Downtown Aurora Campus. 

Summary

As Waubonsee Community College’s total site construction partner, Abbey worked closely with the client to make critical infrastructure upgrades at their Downtown Aurora Campus. During the design approval phase, we coordinated with the owner to ensure all existing conditions matched the intended design, while creating multiple mockups to help the client visualize the end product and make decisions with confidence. Later, Abbey performed various construction services at key locations across campus.  

Project Scope

  • Demoed and replaced concrete stairs.
  • Removed and reinstalled stainless-steel railings.
  • Supplied a new ADA ramp with a stainless-steel railing.
  • Removed, refabricated and reinstalled overlook railings on existing retaining wall.
  • Saw-cut, removed and replaced top portion of existing colored, textured wall.
  • Removed existing coping stones and replaced with new prefabricated coping stones on existing retaining wall.
  • Stamped and stained concrete